| New central logistic center |
| General Informations |
| Investment | 10 millions Euro incl. building, building work and adjustment |
| Capacity | ca. 750.000 aluminium wheels and summer- and wintertyres |
| Paces of workstations | normally ca. 40 workstations - in the saisons up to 60 workstations |
| Building history | July 2007 - issue of building license September 2007 - announcing the building project in Frankenthal August 2007 Begin the building March 2010 - Finishing the building |
![]() |
![]() |
![]() |
![]() |
| Building informaton |
| Stock | Length: 115,78 m Width: 68,86 m Height: 16,83 m + 1,20 m ramp heigth |
| Office | Length: 73,52 m Width: 8,89 m Height: 13,16 m Office total: 3.052,56 m² |
| Outwall, roof, sectionaldoors and windows | each thermal insulation, substitution of insulation glass |
| Roof drain | Drain in infiltration on the building - Biotope |
| Fire Protection | 123 fire detector, total Objekt is equipped with the modern fire alarm system. |